NIS2 · CASE STUDY

Sign off a restored service

Check measurement values, data quality and acceptance in the HanseWerk practice case.

SCOPE
IMPLEMENTATION
EVIDENCE

Your job for the re-start exercise

In the fictitious HanseWerk, order processing must be professionally usable within 90 minutes. Up to 15 minutes of data loss are allowed in the exercise target. The department expects all 10.000 reference data sets to be checked.

In the first run, the application can be reached after 75 minutes. However, a complete business process only succeeds after 105 minutes. The restored data level is eight minutes before the failure and contains 9.998 of the 10.000 reference data sets

So you go ahead

  1. Determine whether or not the data are collected separately

    Provide technical information, technical usability, data level, quantity and acceptance as separate information. The department confirms the relevant sources.

    Work result Comparison of the measured values with the approved target.

  2. Deviation until the responsible remedy

    Keep the time and missing data sets separately. Check which remedy is needed for data and technical process and who is responsible for it.

    Work result Two comprehensible findings with correction.

  3. Reexamine the same technical standard

    Let the business process be repeated after a coordinated follow-up and compare data status and records with the same criteria.

    Work result Decision from comparable measurement and technical acceptance.

Findings on this work path

Technical resumption requires the examination of time, data level and executed business process.
Technical resumption requires the examination of time, data level and executed business process.

Technical resumption requires the examination of time, data level and executed business process.

Reasoned decision and counter-probe

Situation In the fictitious HanseWerk, order processing must be professionally usable within 90 minutes. Up to 15 minutes of data loss are allowed in the exercise target. The department expects all 10.000 reference data sets to be checked.

Situation

The re-start time is 15 minutes. The goal for maximum data loss is met. The complete sample fails due to two missing records. The release remains open, although the application is technically achievable.

The application can be reached after 75 minutes. The first run reaches the compartment after 105 minutes and misses the 90-minute goal. The subsequent test reaches it after 82 minutes.
The application can be reached after 75 minutes. The first run reaches the compartment after 105 minutes and misses the 90-minute goal. The subsequent test reaches it after 82 minutes.

The time for technical usability is measured from the same starting point in both runs. Data age and completeness have their own test criteria.

Negative test

In the post-test, the partition process succeeds after 82 minutes, the data level is seven minutes before failure and all 10.000 records are available. Document separate partition release and check as a counter sample whether the time limit alone would suffice for release.

Work aids for your operation

Use the predictable template and check the result with the fully described example.

  • Restart and restoration

    Restart and data loss. Check data integrity, partition process and release separately.

    Outcome Evidence of the professional resumption or a reasoned open finding.

    Read the instructions

    Fictional example The first run takes 105 minutes instead of 90 minutes and delivers 9.998 data sets from 10.000. In the subsequent test, the subject sample must be time and content.

    1. Set target values Decide on permitted time, data loss and expected records at the service.
    2. Record readings Determine technical usability only with a executed process as achieved.
    3. Check data and release The following shall be used for the purposes of this Regulation:
  • Measures and efficacy samples

    Arrange the ten fields of action. Treat test criteria, measurement, detection, findings and retest in the same work position.

    Outcome Summary of measures with observed effect and pending retests.

    Read the instructions

    Fictional example A back-up is achieved in 88 minutes. The sample from the department is missing. The measure remains open until the agreed result is fully documented.

    1. Select criterion and type of test The ten action fields bear prepared examples. Set the appropriate yes-no criterion or a measurable setpoint.
    2. Record impact and evidence Refer to the target and is on the same performance and the relevant time.
    3. Track deviation and follow-up Record correction order, re-result and receipt with the same verification identifier.

Official references for this task

First check for this task

Other official references1

Check time deviation and technical acceptance in your own service

Management

You must jointly examine time, data and technical resumption.

The same exercise is used to demonstrate the re-start time, data level and technical acceptance.

Work result A reasoned decision to resume with measured time value, data level and subject sample.

Evidence and supervision

They shall provide evidence of the audit mandate for management, internal audit or oversight.

Merge test order, efficacy test, deviation and follow-up test.

Work result A second person can understand the findings and clearance decisions from the sources.

Management

A decision by the management is missing for action or follow-up test.

Decision, implementation, monitoring and training of specific services

Work result A management mandate with responsibility, target criterion and comprehensible monitoring.