CRA · CASE STUDY

Reject a faulty security update

An update reaches all sample devices.

PRODUCT
CONFORMITY
MAINTENANCE

Starting position and test order

A fictitious provider distributes a security update for its temperature sensors. Internal acceptance requires four successful installations with subsequently confirmed warning function and a documented rejection of a test package without valid assignment to the device series.

Four devices accept the intended package and meet the warning test. The counter sample has been performed with a second matching package instead of the prepared inadmissible variant. The published user guide was checked at the normal download path.

Compare test data and consequences

  • Adoption

    Scale
    4 matching devices
    Observation
    4 updated and operational
    Follow
    Positive sample passed
  • Rejection

    Scale
    1 unsuitable test package
    Observation
    Second matching package used
    Follow
    Effective counter-test missing
  • User access

    Scale
    Update and guidance available
    Observation
    Retrieval confirmed
    Follow
    File and guide occupied

Three separate safety samples

Adoption of a planned package, rejection of an unsuitable package and further function are three separate test criteria.
Adoption of a planned package, rejection of an unsuitable package and further function are three separate test criteria.

Set the scale in advance. Support the functionality even after the intended rejection.

Edit the test step by step

  1. Supporting the planned update path

    Identify delivered device, status before update and released download including user notice.

    Testable evidence Proof that the same version is delivered and tested.

  2. Monitoring adoption and effect

    Log the installation for each of the four sample devices and confirm the warning function based on previously defined observations.

    Testable evidence Four positive samples with a frame and functional documentation.

  3. Repeat the correct negative test

    Use the prepared unsuitable test package in the completed test setup and check the documented reference. Confirm that the existing function has been retained.

    Testable evidence Independent counter-test with verifiable result and confirmed function test.

Four successful installations with different findings

Four devices are updated in each run. Only the complete aftertest proves rejection and function.
Four devices are updated in each run. Only the complete aftertest proves rejection and function.

An equal number of successful installations can lead to different release decisions. Check the type of counter-test.

Worked decision and negative test

Decision in case

The appropriate update has arrived at four devices. However, the counter-test checks the wrong condition in the first run. The release remains open until the unsuited artifact is rejected.

Perform the new run with the same output frame and a realistic, completed distribution path. Hold that after the rejection the device remains in operation at the intended level.

Counter-sample and impact

If you detect a confirmed rejection, leave the proof of the warning function after the update empty. Update acceptance and protection against the unsuitable package are observed. The release of effects remains open due to the lack of functional evidence.

Templates and worksheets

  • Security update and negative test

    Document the target, delivery identity, acceptance, referral and unchanged product function in the post-test.

    Outcome Test file for a concrete update with independent test results.

    Read the instructions

    Fictional example Four devices accept the intended update. The first test case used does not confirm the rejection.

    1. Identify the starting situation Identify the released package and device capture.
    2. Run the test Detection of acceptance, counter-sample and product function separately.
    3. Secure decision and evidence Document first run and corrected repetition independently.

Official sources

What depends on your result?

  • Decrease security update with negative test

    Transfer the same test criteria to your own product and save the different starting data.

    View the guide
  • Coordinate vulnerability disclosure

    Once the security update is actually available, users need a suitable and understandable information.

    View the guide
  • Release laboratory

    Practice the same decision when a complete or incomplete counter-test is performed.

    Start exercise