DORA training modules
Test the checks and test decisions in the team.
PRACTICE
EVIDENCE
Train test decisions with small cases
Edit short tasks, compare your decisions and keep track of your own documents.
Start with an exercise that actually occurs in your team. One person justifies the decision, a second one asks for proof. Then use the deeper work path for open questions and see how you would check the same situation in your own company.
What you hold Twenty practice decisions with feedback and matching worksheet or web-test path.
Validity and direction
Requirement of legal entities and activities
The company operates the technical process, its own approval is open. Which source and who confirms the decision?
Model response Check registration or registry receipt and proof of performance. The responsible compliance role documents the legal category and open points.
Proportionality
A smaller company wants to reduce the number of test routines. What is the reference to a change?
Model response Demonstrate the size, risk profile, nature and complexity of the controls that are actually required. To maintain responsibility, reasons and resubmission.
Prove management responsibility
A resilience target is mentioned in the annual plan. A measurement and treatment of deviations are missing. What is included in the decision?
Model response Specify observable objective, responsible role, intended examination and release of the follow-up measure.
Connecting the ICT framework with evidence
One guideline calls the goal for recovery. The service report measures another key figure. How is the reference closed?
Model response The technical target to be traced back to the function, service and test protocol in fact.
ICT protection and operation
Assigning functions and assets
The inventory still calls the previous memory after a migration. What do you need to correct?
Model response Compare confirmed function reference, released state of change and technical actual evidence. Historize the old state with end date.
Prove protective measures
A protected export copy remains after the move. What final information is required?
Model response Document classification, location, storage decision, jurisdiction and proof of the released treatment.
Check access and cryptography
A certificate expires, the person responsible is absent. Which checkpoints are required before switching?
Model response Record current process data, representation, approved renewal and professional sample of the certificate change.
Identifying capacity bottlenecks
Normal server load is accompanied by long waiting times for payments. What additional key figure is required?
Model response Choose a technical measure, for example measured waiting time in the payment acceptance. Limit, period and corresponding response prove.
Track Warnings and Processing
A test event is in the protocol. The person responsible has not received an alarm. What proof is missing?
Model response The notification and acceptance of the warning shall be confirmed. After correction, re-examine the same alert threshold.
Restart and reporting
Prioritize business continuity
Two functions use the same platform. What criteria determine the order of restart?
Model response take into account the consequences of failure, critical deadlines, dependencies and restoration available in the concrete process.
Evaluate back-up on two objectives
Payment is possible after 105 minutes. Targets are 90 minutes and a maximum of 15 minutes data gap. Measured is 11 minutes data gap.
Model response The internal time target is missed, the data goal is met. Repeat both criteria separately in the aftertest.
Emerging an incident with data
The specialist page complements the number of users affected after the first ICT findings. How is the decision continued?
Model response Secure the confirmed inventory with its reference size, re-evaluate relevant criteria and document time and reason for change.
Determine the right time-limit
Knowledge at 09:15 o'clock, classification at 11:30 o'clock. What is the regular time limit first?
Model response In the example, it falls on 15:30 on the same day. The 24-hour limit is the following day. The message will be sent as early as possible.
Tests, contracts and remedies
Deriving tests from a technical risk
When changing memory, an alarm should enter and the application should remain accessible. Is a screenshot of the start image enough?
Model response Accessibility and alarm delivery are two criteria. Both receive measurement condition, result and proof.
Control Threat-Oriented Tests
A change in the scope of the test affects another business performance. Who needs what information?
Model response The roles provided for in the control framework evaluate impact and change. Release, expiration and final receipt are assigned to the same file.
Evaluate third-party service provider before the contract
The provider proves performance and costs. The actual dependence on the restoration is open.
Model response The responsible role clarifies the recovery path and its effect on the function. It documents a release with verifiable conditions or another decision.
Validate an information register
The stock and registers contain a lot of contract codes. However, an identification indicates an excluded contract.
Model response The difference list must show a missing and an additional contract, even if the number is equal.
Evaluate subcontracting and contracts
The provider announces a change. An indication of the evasiveness is missing. How does the test proceed?
Model response Secure notification and deadline, request information, evaluate changes before implementation on the basis of functional relevance and demonstrate decision.
Test Concentration and Exit
Two providers both use the same recovery. What assumption does the evasiveness check?
Model response Retrieve the failure of the common platform. Determine alternative, time and usability by means of an independent path.
Confirm remedy after examination
A new form template is intended to prevent missing information. Which sample can confirm the effectiveness?
Model response Check new processes after introduction. A recorded reference must be part of the actual inventory version and release.